Project Description:

Plan, Design & Construct WTP improvement to meet regulatory requirements and meet water use forecast as defined in the March 2009 Water Supply Master Plan. R.O. facility will need to be completed in phases through permitting and testing.

Phase I & II - Permitting & Well Fields

Phase III - Permitting & Injection Well

Phase IV - Permitting & R.O. Facility

Project Update:

As of 7-21-17

  • Well drillers have complete the deep injection (brine disposal) well and have begun drilling the associated monitoring well.  Two water production wells have been completed and the required aquifer performance testing is ongoing.

Project Area Location :

Water Treatment Plant