Project Description:

Construction of a 20 foot Harborwalk in Gilchrist Park beginning at Harvey Street and continuing to the western extinct of Gill Street (Conquistador Statue).  The project will also include

  • Decorative seating area south of existing gazebo
  • Large & small pavilion
  • Brick courtyard area
  • Brick intersection improvements on Harvey, Durrance, & Gill St.
  • Parking enhancements
  • New Seawall
  • Stormwater management system
  • Landscape improvements & irrigation
  • Decorative site lighting
  • Park Amenities including grills, trash receptacles, picnic tables, and flag pole

Gilchrist Park Concept Plan

Project Update:

PicMonkey Collage
New Picture
New Picture (1)

 05/27/2017

New seawall installation and cap continues. Concrete curb installation and crosswalk installation is under way. Shell base is prepped in the diagonal parking areas. Deco light poles and bases have arrived. Material testing is on-going per the FDOT approved plan. The road will remain closed through July 17, 2017 and park will remain closed through December 2017. Pedestrians are requested to seek alternate routes and respect the contractors work zone for their safety.

 

Project Area Map:

400 W. Retta Esplanade

Punta Gorda, FL  33950

Gilchrist Park: Harvey Street to Gill Street

Gilchrist Area One

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer